A 320 m viaduct pushed over the M6 with the traffic still running
HS2 has to cross the M6 near Birmingham, one of the busiest stretches of motorway in the country. Closing it for weeks to lift in a bridge was not an option.
So the contractor, Balfour Beatty VINCI, built each steel deck in sections behind one end of the crossing. Strand jacks, hydraulic jacks that pull on bundles of steel cable, then hauled the deck out over the road in stages. Each push added length at the back and moved the front further across. The west deck went over in four stages; the last one moved it 76 m in nine hours, on 24 October. There are two decks, each 320 m long, sitting 100 mm apart on concrete piers. The M6 stayed open the whole time.